After a short break due to the rainfall in April, the works in the Maternity and Physiotherapy wards have started again.


Maternity:

The windows have been fixed and set to embed the window glasses; the covering of the bathrooms walls with the tiles are completed.
The inner walls and the wooden frames of the doors have been painted.

The works for electrical and hydraulic systems are still in progress.




Physiotherapy:
All the doors and the windows have been fixed, the walls and the columns have been plastered; the treatment for the external walls has been completed.
The hydraulic system is finished; the floor covering of the gym in the Physiotherapy ward has been plastered and smoothed.
The setting of the tiles on the walls of the bathrooms and the locker rooms has been completed.


Look the photo album on Facebook>>>


Helena Pes
Project Manager WF Nairobi

Posted: 5/21/2010 4:52:33 PM by Silvana Merico1 | with 0 comments